Connect recovered-liquid characterization, conditioning, generator selection and electrical integration in one project scope.

YUSHUNXIN ENERGY INTEGRATION

Match pyrolysis-oil conditioning to the generator and operating duty.

Tire-derived and plastic-derived liquids differ in sulfur, solids, viscosity, light fractions and wax behavior. The generator package must be selected after fuel sampling and an agreed conditioning route.

Reference continuous pyrolysis line connected to downstream energy use
01 / FUEL PATH

Do not connect raw recovered liquid directly to a standard genset by assumption

The conditioning train should be based on representative fuel analysis and the engine supplier's written limits.

  1. 01Settling and bulk separation
  2. 02Filtration and solids control
  3. 03Water separation
  4. 04Temperature and viscosity conditioning
  5. 05Day-tank and fuel-supply control
  6. 06Compatible engine and exhaust system
02 / DESIGN QUESTIONS

Make the fuel and electrical boundaries explicit

A practical proposal connects fuel variability, generator duty and site infrastructure.

Fuel characterization

Analyze density, viscosity, ujë, sediment, sulfur, flash point, distillation behavior and any wax or halogen concern.

Engine compatibility

Confirm whether the application requires a heavy-fuel, dual-fuel or other approved engine configuration.

Duty profile

Separate continuous base-load, variable-load, standby and islanded-power applications; they impose different controls and redundancy.

Electrical integration

Define voltage, frequency, synchronization, transformer, switchgear, protection and any grid-connection requirements.

03 / OPERATING SAFEGUARDS

Plan storage, fire protection and emissions with the generator package

Commercial evaluation remains conditional on the local fuel classification and permitting route.

Storage and transfer

Use compatible tanks, bunding, ventilation, temperature control, filtration bypass management and spill response.

Quality release

Set a fuel release test and reject route so off-spec batches do not reach the engine.

Maintenance model

Budget for injectors, filters, lubricant monitoring, deposits and exhaust after-treatment based on actual fuel quality.

Bilanci i energjisë

Compare recoverable fuel, internal thermal demand, generator consumption, auxiliary loads and usable net electricity.

KONFIGURIMI I REFERENCAVE

Përktheni faktet e projektit në një listë të pajisjeve.

Kjo matricë referimi tregon logjikën e vendimit. Sasitë përfundimtare, modelet dhe ndërfaqet i përkasin projekt propozimit të miratuar.

Blloku i sistemitShtrirja tipikeBaza e konfigurimit
Bulk fuel handlingSettling, storage, bunding and controlled transferFuel classification and representative analysis
Conditioning skidFiltration, water separation and temperature or viscosity controlWritten engine fuel limits
Fuel supplyDay tank, circulation, matjen, isolation and reject routeDuty cycle and off-spec management
Generator packageCompatible engine, controls, exhaust and safety systemsApproved fuel, load profile and maintenance basis
Electrical and heat recoverySwitchgear, protection, synchronization and optional heat interfaceSite electrical boundary and usable energy demand
RRUGA E VENDIMIT ME FAZA

Përparoni projektin vetëm kur provat e kërkuara janë të disponueshme.

Çdo portë e kthen informacionin e klientit në një rezultat të përcaktuar teknik ose tregtar për vendimin e ardhshëm.

01

Fuel evidence

Sample the recovered liquid and define batch variability.

ProdhimiFuel-analysis and classification record
02

Compatibility review

Compare the analysis with written engine and conditioning limits.

ProdhimiApproved fuel-conditioning boundary
03

Site integration

Define duty, electrical protection, storage, fire and exhaust interfaces.

ProdhimiSingle-line and interface basis
04

Commercial proposal

Quote only against the approved fuel, duty and delivery boundary.

ProdhimiTraceable configuration and exclusions
FAQ PËR PROJEKTIN

Pyetje për të zgjidhur përpara konfigurimit.

Përgjigjet përcaktojnë kufirin inxhinierik; ato nuk zëvendësojnë testimin e materialit përfaqësues ose rishikimin lokal të pajtueshmërisë.

Can untreated pyrolysis oil be used in any diesel generator?

No. Analiza e karburantit, conditioning and written engine compatibility limits are required. Standard high-speed diesel engines should not be assumed compatible.

What fuel tests should be prepared?

Typical evaluation includes density, viscosity, ujë, sediment, sulfur, flash point, distillation behavior and any wax or halogen concern.

What is included beyond the generator?

The project may require settling, filtration, water separation, temperature control, storage, day tanks, fire protection, switchgear, synchronization and exhaust treatment.

How should net electrical output be evaluated?

Compare usable conditioned fuel, internal thermal demand, generator consumption, auxiliary loads, operating duty and electrical losses under the agreed project basis.

SHQYRTIM INXHINIERIK I PROJEKTIT

Përcaktoni materialin përpara se të zgjidhni pajisjen.

Ndani një përshkrim material përfaqësues, vëllimi i disponueshëm, statusi i faqes dhe rezultatet e synuara. YUSHUNXIN do t'i përdorë ato fakte për të përgatitur diskutimin përkatës të kufirit të procesit dhe konfigurimit.

Filloni rishikimin e projektit